A well is built in a tight sequence: drill, case, cement, complete, test and hand over. Equipment arrives from several manufacturers, is installed by several crews, and is expected to hold pressure for years. Drilling and completion well inspection is the discipline of checking, at each handover in that sequence, that the item is what was ordered, that it is in the condition the records claim and that the installation was recorded properly.
This article explains what a typical inspection scope covers, how the wellhead and tree standard defines its own limits, where gaps appear between standards and contracts, and what an independent inspector can and cannot do at a rig site. It is aimed at operators and service companies in Indonesia that buy equipment from overseas and want the inspection scope to match the real risk.
- Two phases, one chain of custody
- What a completion contains
- Wellhead and tree equipment under ISO 10423
- The gaps between standards
- Rig-side equipment and lifting
- The as-run record
- What the inspector does at the rig site
- Frequently asked questions
Two Phases, One Chain of Custody
Drilling creates the hole; completion makes it a usable well. According to the general description of well completion, completion includes preparing the bottom of the hole, running production tubing and downhole tools, and perforating or stimulating the formation as needed. The two phases use different equipment, but they share one problem: each item passes through many hands before it ends up downhole.
That chain of custody is where inspection earns its place. A component can be correctly made and still arrive with the wrong serial number on the paperwork, a damaged seal surface or an expired test record. Because the work is sequential and expensive to interrupt, a discrepancy found on the drill floor usually costs far more than the same discrepancy found in the yard.
Inspection therefore works best as a series of small, defined checks, not as one large inspection at the end. The questions are the same at each point: what is it, is it the right item, is it undamaged, and is the record complete.
What a Completion Contains
The standard components are easy to list. Casing keeps the hole from collapsing and protects the wellstream. Production tubing carries fluids to the surface, packers seal the annulus between tubing and casing, the wellhead supports the casing strings and connects the blowout preventer or the Christmas tree, and the tree controls flow. Subsurface safety valves act as a last-resort barrier against uncontrolled release.
Each component has its own risk profile and its own inspection stage. Tubulars are inspected at the mill, at the threading shop and on receipt. Downhole tools are typically inspected at the manufacturer or service company’s base, with pressure tests and function tests recorded. Surface equipment such as the wellhead and tree goes through factory acceptance testing before shipment and a final check on site.
An inspection plan for a completion should list every major item, the stage at which it will be checked, the person or party who will attend, and the record that results. A plan that says only “inspect completion equipment” leaves each of those four questions to be settled at the last moment.
Wellhead and Tree Equipment Under ISO 10423
The reference for surface wellhead and tree equipment is ISO 10423. According to ISO, the 2022 edition (the fifth) covers requirements and recommendations for wellhead and tree equipment, including performance, interchangeability, design, materials, testing, inspection, welding, marking, handling, storage, shipment and purchasing. It supplements API Spec 6A, 21st edition (2018), and replaces the 2009 edition.
That list shows what a purchaser can expect the standard to govern at the factory: how the equipment is made, tested, inspected and marked, and how it is handled before delivery. It does not tell you what condition a particular item is in when it arrives at your yard, or whether the right model was shipped against your order. Those remain matters for your own receiving inspection and documentation review.
A practical consequence is that the purchase order should state the standard edition, the product specification level, the pressure and temperature ratings, the material class for the service and the documents to be supplied. As with other equipment, what the order does not say cannot be enforced afterwards.
The Gaps Between Standards
The same ISO page states what ISO 10423 excludes: field use and field testing, repair other than weld repair during manufacturing, and installation or service tools such as running and test tools. This matters because those excluded items are exactly the ones used on the rig. A tree can be perfectly compliant while the tool used to run its hanger is damaged or out of calibration.
Buyers sometimes assume that “compliant with the standard” covers everything on the well. It does not. The wellhead standard stops at the equipment’s delivery condition, tubular standards stop at the pipe and its threads, and running tools, torque equipment and test pumps each have their own rules, if any. A good inspection scope therefore names the tools and services that sit outside the main standards and says how they will be verified.
The same goes for repair and redress. Equipment that has been in service and returned for reuse falls outside a manufacturing standard, so the acceptance criteria for reuse should come from the owner’s procedures or the manufacturer’s instructions, and the contract should say whose.
Rig-Side Equipment and Lifting
The rig itself is part of the inspection picture. Lifting gear, slings, shackles, elevators and handling tools all carry certificates and inspection tags that expire, and they are in constant use. A failed lifting device on the drill floor is a safety event as well as a quality problem, so the status of every lifting item used for completion work should be checked before running begins.
A rig assessment looks at a different question: whether the rig and its equipment are in a condition and arrangement suitable for the job. G.I Quality Services lists both drilling and completion well inspection and rig assessment or surveyor services among its offerings, which shows that this scope is recognized as a distinct service. What a given provider will actually assess should be agreed in writing, including the checklist and the standards it refers to.
Where equipment is leased from a service company, ask for its current inspection and calibration records as part of mobilization. A short, early review of those records usually costs less than a delay at the rig.
The As-Run Record
The most valuable document to emerge from a completion is the as-run record: a list of what was actually installed, joint by joint and component by component, with serial numbers, lengths, depths and the date and crew for each step. It is the bridge between the design on paper and the well in the ground.
A good as-run record can be reconciled in both directions. Every item should trace back to a certificate or data book entry, and every certificate should be tied to an item that was actually run. Gaps are the warning sign: a serial number in the record with no certificate, or a certificate for something that was never installed, suggests either an error or a substitution.
Future workovers depend on this document. Engineers planning an intervention years later will rely on the recorded dimensions, depths and materials to choose tools and procedures. An incomplete record at handover can turn a straightforward job into an expensive investigation.
What the Inspector Does at the Rig Site
At the rig, an inspector usually performs three kinds of task. First, verifying items against records before they are run: identification, condition and status of the certificates. Second, witnessing defined activities, such as make-up of connections, pressure tests and function tests, against the agreed procedure. Third, recording what was seen in a consistent format, including photographs and the identification of items.
Equally important is what the inspector does not do. An inspector does not take over well-control decisions, does not instruct the drilling crew on operational matters outside the scope and does not sign off on engineering changes. If the inspector finds something that appears wrong, the right action is to stop the activity through the agreed channel, notify the responsible person and record the event.
Logistics shape the work. Rig sites, especially offshore, impose safety induction, transport limits and work permits, and the inspector must be competent and cleared to attend. When specifying scope, ask the provider about the qualification of the people who would attend and how their reports reach the head office. Remote or foreign management benefits most from a clear, repeatable report format.
Frequently Asked Questions
What does drilling and completion well inspection cover?
It covers the checking of equipment, materials and activities across drilling and completion: documents, identification, condition, witnessed tests and installation records. The exact scope depends on the contract and the inspection plan.
What is ISO 10423?
According to ISO, it is the standard for wellhead and tree equipment, covering design, materials, testing, inspection, welding, marking, handling, storage, shipment and purchasing. The 2022 edition is the fifth and supplements API Spec 6A.
Does ISO 10423 cover running tools and field repairs?
No. ISO states that it excludes field use and field testing, repair other than weld repair during manufacturing, and installation or service tools such as running and test tools. These need separate verification.
What is an as-run completion record?
It is the record of what was actually installed in the well, with serial numbers, lengths, depths and dates. It should trace each item to a certificate and is essential for later workovers.
Can a third-party inspector stop work on a rig?
An inspector can raise concerns and request that an activity be stopped through the channels agreed in the contract, but does not take over operational or well-control decisions. Agree the authority and the reporting line in advance.
How should an inspection plan for a completion be organized?
List each major item, the inspection stage, who attends, the acceptance criteria and the record produced. Include tools and services that fall outside the main equipment standards.